Intro:
Once you’ve secured a planning permit (if required), the next step is obtaining a building permit. This document, issued by a registered building surveyor, confirms that your extension plans comply with the National Construction Code (NCC), the Building Act 1993, and the Building Regulations 2018. Without it, construction cannot legally begin.
1. What is a Building Permit?
A building permit is your official go-ahead to start construction. It’s not just paperwork — it’s a quality and safety checkpoint, ensuring your plans meet legal and safety standards.
A building permit will outline:
-
Approved drawings and specifications
-
Mandatory inspection stages (e.g., footing, frame, waterproofing, final)
-
Permit validity dates (usually 12 months to start, 24 months to finish)
2. Who Issues a Building Permit?
Only a registered building surveyor (private or municipal) can issue a building permit.
-
Private building surveyors are often faster and more flexible with scheduling inspections.
-
Council building surveyors may suit smaller projects or if your council has specific approval preferences.
3. What Documents You’ll Need
Before the surveyor can issue the permit, you must provide:
-
Planning permit (if applicable)
-
Working drawings and specifications
-
Structural engineering drawings and computations
-
Soil report (geotechnical assessment)
-
Energy report (minimum 6-star rating)
-
Title search and plan of subdivision
-
Easement consents (if applicable)
Tip: Alert Engineers can prepare permit-ready drawings, structural calculations, and soil testing packages.
4. The Application Process
-
Choose Your Building Surveyor
– Must be independent of the builder unless appointed by the owner. -
Submit Documents
– Include all required approvals, reports, and drawings. -
Assessment by Surveyor
– They may request changes to ensure NCC and Regulation compliance. -
Permit Issued
– You can now legally commence construction.
5. Mandatory Inspections
Your building permit will list inspection points. For an extension, this might include:
-
Footing/Slab inspection before concrete is poured
-
Frame inspection before walls are enclosed
-
Waterproofing (particularly in bathrooms and balconies)
-
Final inspection before occupancy
Missing an inspection can void the permit, delay completion, and result in fines.
6. Common Reasons for Permit Delays
-
Missing planning permit (if required)
-
Incomplete or inconsistent drawings
-
Failure to obtain report-and-consent from water authority or council for easement works
-
Engineering not aligned with architectural design
7. After the Building Permit
Once issued, you can start construction with your chosen builder. For a smooth process:
-
Schedule inspections early to avoid delays
-
Keep a copy of the permit and approved plans on site at all times
-
Ensure all changes are approved before being built
-
Need complete drawings and engineering? Alert Engineers prepares full building permit packages.
-
Want a design-and-build solution? Alert Construction handles the entire extension process from planning to handover.
-
Learn about council-specific requirements here → Melbourne Council Rules You Must Know Before Building